WBS Planner
by @ycz87
Work Breakdown Structure for multi-agent project management. Organize work as Roadmap → Epic → Task hierarchy with templates and granularity standards. Use w...
clawhub install wbs-planner📖 About This Skill
name: wbs-planner description: "Work Breakdown Structure for multi-agent project management. Organize work as Roadmap → Epic → Task hierarchy with templates and granularity standards. Use when: (1) planning project work and breaking features into tasks, (2) creating or updating roadmaps, epics, or task specs, (3) reviewing task granularity before dispatch, (4) organizing project documentation structure. Triggers: roadmap, epic, task breakdown, WBS, work breakdown, project planning, task spec."
WBS Planner
将项目工作从宏观到微观逐层分解:Roadmap → Epic → Task。
三层结构
| 层级 | 定义 | 负责人 | |------|------|--------| | Roadmap | 产品路线图,规划所有 Epic 的优先级和时间线 | 创始人 / PM | | Epic | 大功能模块,包含多个 Task | PM 规划 | | Task | 可分配给单人、1-2 个工作周期内完成的具体任务 | PM 创建,Dev 执行 |
项目目录结构
在项目根目录下创建 roadmap/ 目录:
roadmap/
├── roadmap.md
├── epic-001-feature-name/
│ ├── epic.md
│ ├── task-001-name.md
│ ├── task-002-name.md
│ └── task-003-name.md
├── epic-002-feature-name/
│ ├── epic.md
│ └── task-001-name.md
└── ...
命名规则:
epic-NNN-简短英文名task-NNN-简短英文名.md模板文件见 templates/ 目录。
Task 粒度标准
这是整个体系的核心。Task 拆得不够细,验收就容易失败。
一个合格的 Task 必须同时满足:
1. 单一交付物 — 只做一件事,只验收一件事 2. 验收可量化 — 条件具体到操作步骤,不是"看起来不错" 3. 体量可控 — 预计 1-2 个工作周期完成,超过则继续拆 4. 独立可测 — 不依赖未完成的其他 Task
判断示例:
→ 更多拆解指导见 references/breakdown-guide.md
角色工作流
详细操作流程按角色拆分,按需加载:
与团队协作协议的关系
本 skill 管"做什么":层级、拆解、模板、文档结构。 团队协作协议(如 agent-team-orchestration)管"怎么协作":状态流转、交接协议、评审规则。 两者互补,不重叠。